Install FR800 Mechanical Meter in 27 steps.
Directions to Install FR800 Mechanical Meter Full Rebuild Kit
Disassembling Meter
- Slide off reset knob
- Remove (2) fasteners from front of meter
- Remove face plate
- Remove the register cover
- Remove (2) fasteners and remove register
- Flip meter over, remove (4) fasteners from meter housing
- Remove o-ring, chamber assembly, gear frame, gasket
- Remove cluster gear, washer, shaft
- Remove drive gear, washers, o-ring, pinion bevel
Calibration Cap and Screw
- Place o-ring onto drive gear shaft
- Install drive gear into meter
- Install pinion bevel on other side of drive shaft to secure in place
- Place washer onto drive shaft
- Install cluster gear shaft into the meter
- Install cluster gear and washer onto shaft
- Place small washer onto shaft
Installing Gear Frame and Chamber Assembly
- Install cover gasket
- Install gear frame, ensure notches align with holes in casting
- Install chamber assembly
- Install remaining gasket onto chamber assembly
Reassembly of the Meter
- Place meter housing onto meter cover
- Secure (4) fasteners, tighten to at least 100 in-lb
- Flip meter housing and cover over
- Align register mounting tabs with holes on meter cover, secure with (2) fasteners
- Place register cover on meter, secure faceplate on cover with (2) fasteners
- Slide reset knob back onto reset shaft
Replacing Inlet Gasket
- Place new gasket in indentation, reinstall flange